Valve test system
Type
F [1 - 3]: VPS: Load valve
F [1 - 3]: VPS: Load time
F [1 - 3]: VPS: Relief valve
F [1 - 3]: VPS: Relief time
VPS: Calculating the testing times
F [1 - 3]: VPS: Fuel valve 1: Proof time
F [1 - 3]: VPS: Fuel valve 2: Proof time
F [1 - 3]: VPS: Valid time
F [1 - 3]: VPS: Fuel valve 2: Delayed close
Parameter
Description
The following parameters are used to define whether the pressure in the test segment is built up via main gas valve 1 or via a separate charging valve.
If a separate charging valve is used for the valve test, FSC configuration for digital outputs must contain the "Charging valve" output signal:
Fuel 1: Charging valve
Fuel 2: Charging valve
Fuel 3: Charging valve
Properties
Selection parameter
Reference
1074; 1023; 1354
DOC-728915490